PJM 计划增加 15 吉瓦电力供应以满足数据中心的需求增长。
PJM Targets 15 Gigawatts Of New Power To Feed Data Center Boom

原始链接: https://www.zerohedge.com/markets/pjm-targets-15-gigawatts-new-power-feed-data-center-boom

PJM互联,管理美国最大的电力网络,正紧急寻求15吉瓦的新电力供应,以满足人工智能数据中心快速增长的需求。这项紧急提案涉及将拟建的数据中心与新的发电厂建设直接连接,最早下周开始。 该举措凸显了人工智能爆炸式增长对电网造成的压力,超过了之前的负荷预测,并推动了创纪录的即期电力价格。PJM预计未来十年将出现60吉瓦的电力缺口。 然而,这一时机受到了批评,被认为具有矛盾性:在寻求新容量的同时,PJM也在推迟近乎完工的800兆瓦克兰清洁能源中心(前三英里岛)的全面整合,可能将其运营日期推迟至2031年。这引发了人们对PJM整体战略的质疑,因为它在满足即时需求与现有、可用的能源之间取得平衡。15吉瓦计划的成功取决于能否从开发商那里获得明确的承诺。

相关文章

原文

PJM Interconnection, operator of the largest power grid in the United States spanning 13 states and serving more than 65 million people, has launched an emergency proposal to secure 15 gigawatts of new electricity supply, according to Bloomberg. The move aims squarely at the surging AI data center demand, which has pushed the regional grid to its limits. The plan calls for bilateral negotiations to pair proposed data centers with new power plants.

PJM will begin gauging interest from developers and generators late next week, with the formal matching process running from September 2026 through March 2027. The grid operator described the initiative as a targeted response to potential shortages driven by the AI boom, which has accelerated load growth far beyond earlier forecasts.

We've been highlighting the growing strain on national grids like PJM for years now. Data centers are the dominant forces reshaping regional power markets, contributing heavily to capacity costs in recent auctions and forcing operators to scramble during winter peaks.

Spot power prices have already hit records above $1,000 per megawatt-hour

Explosive demand from hyperscalers' facilities in Virginia, Pennsylvania, and surrounding states continues to outpace new generation additions With shortfalls of 60 GW over the next decade.

The timing of this emergency proposal, however, adds a layer of absurdity. Just weeks ago, PJM informed Constellation Energy that transmission project delays could push full grid deliverability for the restarted Crane Clean Energy Center, formerly Three Mile Island Unit 1, out to 2031. That is four years later than Constellation’s target of late 2027 for the roughly 800 MW nuclear plant, even as the facility itself nears readiness. Constellation is now seeking FERC waivers to speed things up.

PJM is scrambling for 15 GW of new capacity while delaying the bolting on of energy sources that are nearly ready to go? We're not exactly sure what the 4D-chess strategy is here.

The 15 GW target represents a significant slice of capacity roughly equivalent to over a dozen large nuclear or gas-fired plants coming online in short order. Whether developers will step up with firm commitments remains to be seen.