## 南方电力报告需求激增,数据中心是主要驱动力 南方电力在2026年第一季度经历了2.3%的零售电量同比增长,创下近期历史新高,这主要得益于数据中心电力消耗量的42%增长。该公司目前已与客户签订了11吉瓦的大型负载项目,另有6吉瓦的项目在推进中,以及75吉瓦的潜在项目储备。 为了满足不断增长的需求,佐治亚电力将资本支出增加到20亿美元,并已申请批准增加2-6吉瓦的容量,包括热力发电、储能和可再生能源等多种来源。 南方电力最近从能源部获得265亿美元的贷款,用于升级和扩展其电网,重点是16吉瓦的稳定可靠电力——包括5吉瓦的新天然气发电、核电改进以及超过1300英里的输电升级。他们还计划通过涡轮机升级增加400兆瓦的天然气容量。虽然对核能感到兴奋,但该公司目前尚未承诺建设新的核电单元。

相关文章

原文

By Diana DiGangi of UtilityDive,

The company has 28 large load projects representing 11 GW under contract, and Georgia Power’s first-quarter capital expenditures increased year over year from $1.6 billion to $2 billion.

Southern Company reported 2.3% year-over-year growth in retail electricity sales across its utilities for the first quarter of this year, driven predominantly by data centers.

Overall, data centers used 42% more power compared to the first quarter of 2025, according to company officials and Southern’s quarterly report to the Securities and Exchange Commission. The company has 28 large load projects representing 11 GW under contract, up slightly from 26 projects at 10 GW at the end of 2025, it said.

Across Southern’s vertically-integrated electric utilities in Alabama, Georgia and Mississippi, its largest subsidiary, Georgia Power, increased its first-quarter capital spending year-over-year from $1.6 billion to more than $2 billion.

Last week, Georgia Power filed a request with regulators seeking an additional 2 GW to 6 GW in new, all-source capacity, including thermal generation, energy storage systems and battery storage plus renewables, to meet rising energy demands.

The 2.3% growth “represents the highest total retail sales growth that we’ve seen in the first quarter in recent history,” said CFO David Poroch on a Thursday earnings call. “The commercial class grew 4.5% in the first quarter when adjusted for weather, bolstered by ongoing growth in data centers.”

BY THE NUMBERS: SOUTHERN COMPANY Q1 2026

  • 11 GW: Total capacity of contracted large loads as of Q1 2026.
  • 2.3%: Q1’s year-over-year increase in retail electricity sales.
  • $2B: Georgia Power’s Q1 capital expenditures.
  • 400 MW: The amount of gas capacity that Southern Company plans to add through turbine upgrades at existing facilities in Alabama and Georgia.
  • $26.5B: The size of the Department of Energy loan package that Southern Company closed on in February.

Outside of signed contracts, Poroch said Southern is finalizing another 6 GW of large load customers and claims to have a “prospective pipeline” of 75 GW, according to its earnings presentation.

“We continue to see incredible momentum and tangible interest for power from large load customers,” said CEO Chris Womack.

The company also provided details on its $26.5 billion loan agreement with the Department of Energy, announced in February, to “build or upgrade over 16 GW of firm reliable power to the electrical grid,” DOE said in a release.

“This includes 5 GW of new gas generation, 6 GW in nuclear improved through uprates and license renewals, hydropower modernization, battery energy storage systems and over 1,300 miles of transmission and grid enhancement projects,” DOE said.

According to its presentation, the company has divided loan-eligible projects by type, with 36% being thermal generation, 21% transmission, 20% distribution and the rest split between hydro, storage and nuclear.

Southern’s work to bolster generation also includes uprates at some of its existing gas generation at plants in Alabama and Georgia that would add 400 MW at a cost of about $700 million over the next several years, “with commercial operation projected between 2029 and 2031,” Poroch said. 

The company is also evaluating an additional 300 MW of natural gas upgrades, Poroch said.

When asked about the potential for upcoming nuclear deals, Womack said that he is “very excited” about the momentum around nuclear, but that the company is “not at a place to make a commitment about building a new unit.”

“We’re going to continue to share the experiences that we gain from Vogtle Units 3 and 4,” he said. “But I’m very thrilled and very excited about the conversations and the commitments and the actions that are being taken, particularly around doing more around AP1000s with a group of companies.”