阿拉斯加州上塔纳纳谷仍在使用中的二战时期电话线(2021年)
World-War-Ⅱ-era telephone line still in use in Upper Tanana Valley Alaska (2021)

原始链接: https://www.sketchesofalaska.com/2021/03/world-war-ii-era-telephone-line-still.html

阿拉斯加军事电话线(AMTL)于二战期间沿阿拉斯加公路修建,是一项全长2,020英里的宏伟工程,连接了艾伯塔省埃德蒙顿与费尔班克斯。该线路于1943年10月完工,整合了无线电、电话和电传打字技术,以确保通信的可靠性,克服了常干扰无线电信号的大气影响。 该项目面临诸多严峻挑战,包括极端的亚北极冬季条件、严重的物资短缺,以及政府强制将铜线更换为效率较低的铜包钢线,这使得工程不得不增设中继站。项目最初由私人承包商承建,但由于各种复杂困难——从解冻的“无底沼泽”到物流延误——最终不得不由美国陆军通信兵部队介入才得以完成。 AMTL总计使用了约95,000根电线杆和14,000英里的电线,是战时工程创造力的见证。如今,尽管公路沿线仍能见到一些倾斜的电线杆作为历史遗迹,但部分原始基础设施仍在为当地提供电话服务。

阿拉斯加州上塔纳纳谷至今仍在使用一条可追溯至第二次世界大战时期的明线电话线路。该线路最初由美国陆军通信兵部队于 1942 年修建,旨在连接阿拉斯加-加拿大公路沿线的军用机场。这项浩大的工程在冰冻的土地上竖立了 9.5 万根电线杆,铺设了 1.4 万英里的电线,且仅用 15 个月便告完成。 近期,该线路的影像在 Hacker News 上引发了讨论,观察者通过识别其特有的老式明线系统导线换位模式,证实了其真实性。此类基础设施在当今依然屹立并正常运作实属罕见,它是战时通信工程中令人惊叹的遗迹。
相关文章

原文

The Alaska Highway, built in 1942, was not the only World War II-era construction project linking Alaska with the rest of North America. The Alaska Military Telephone Line (AMTL), stretching 2,020 miles from Edmonton, Alberta, to Fairbanks was also built during that period.

According to the book U.S. Army In World War II; The Signal Corps, The Test, three communications technologies were incorporated into the project: radio, telephone and teletype. Radio, the most portable, followed Alaska Highway construction crews into the field. However, because of atmospheric and magnetic interference at higher latitudes, radio was not always reliable. Consequently, a telephone and teletype line paralleling the highway was also planned.

Because of wartime demands, U.S. Army Signal Corps personnel (normally responsible for building such systems) were needed elsewhere and could not be spared for the project. Private contractors built much of the line.

The line was approved for construction in June 1942. However, planning consumed the next five months and work could not start until November, about the time the Alaska Highway officially opened.

The first section of AMTL, from Edmonton to Dawson Creek, British Columbia, was perhaps the most difficult to build. Frigid winter conditions meant workers had to bore holes in frozen soil to install poles. Crews were also missing crucial supplies. For instance, 400 miles of poles were installed before crews received crossbars on which to attach the wire.

There were also unanticipated design changes. During World War II copper was designated a strategic raw material, and the War Production Board disapproved the use of all-copper wire for the AMTL, substituting copper-clad steel wire instead. The substituted wire did not provide the same long-distance transmission characteristics, so additional repeater stations were needed.

Myriad other problems delayed construction, including lumber shortages, freak weather conditions, and lack of worker housing. To meet a Dec. 1 deadline for getting the first section operational, only a skeletal system was installed (which required augmentation before proceeding further).

The schedule called for completing the next section, as far as Whitehorse, Yukon Territory by May 1. Correcting deficiencies in the original line, as well as the winter-time construction, slowed line-work considerably. By the end of January 1943, it became evident that the only way to ensure the project’s timely completion was to bring in Signal Corps troops. On March 1, the 255th Signal Construction Company left San Francisco. Corps of Engineer troops were temporarily pressed into service until the Signal Corp troops arrived.

The second section was completed three weeks later than anticipated, on May 22. On that day a call was placed over the line from Whitehorse to Washington D.C..

In early summer 1943 work started on the final section. Weather was favorable and work progressed rapidly along most of the route. There was one 50-mile stretch of particularly bad road just east of the Canada border, however. Corps of Engineer crews had punched through that road section during the previous winter when the ground was frozen. Troops had simply scraped off the insulating muskeg and graded the underlying frozen ground. When the ground thawed in the spring the road became a seemingly bottomless bog. It took a 20-man Signal Corps detachment, supplied by horseback, four weeks to put in that section of line.

By the middle of October 1943 the line was completed. Ken Coates book, North to Alaska, mentions that 95,000 poles and 14,000 miles of wire were used in the project.

Sections of the World War II-era line, some with poles tilting at crazy angles, can still be seen along the Alaska Highway in the Upper Tanana River Valley. Portions of the line are still used for local telephone service.

Sources:

  • North to Alaska, Fifty Years of the World’s Most Remarkable Highway. Ken Coates. University of Alaska Press. 1992

  • U.S. Army in World War II: The Signal Corps: The Test. George Thompson et al. Center of Military History. 2003

联系我们 contact @ memedata.com