为防止电力需求高峰期及大规模维护停电期间可能出现的电网不稳定状况,美国能源部(DOE)发布了一项紧急指令,授权 PJM 互联电网公司要求数据中心等大型电力用户启用其现场备用发电设备。 截至 2026 年 5 月 18 日,超过 40 吉瓦(GW)的电力装机处于维护停机状态,导致即将到来的热浪天气对电网可靠性构成了严峻挑战。根据《联邦电力法》第 202(c) 条,美国能源部的该项指令要求这些大型工业和商业站点切换至备用电源,作为避免轮流停电的最后手段。 PJM 已在其管辖范围内实施了“最大发电量”和“高温天气”预警,并启动了需求响应计划以应对局部电力受限问题。由于预计电力需求峰值将超过 13.5 万兆瓦,美国能源部旨在通过利用这些未充分使用的备用资源,保障电网安全运行并确保公共安全。此举与今年早些时候为其他区域电网运营商发布的类似紧急指令一致,旨在维护系统稳定性。

相关文章

原文

By Ethan Howland of Utility Dive

Power plant and transmission owners often take their facilities offline in the spring for maintenance so they are prepared for the summer, PJM noted. The largest US electricity grid operator said it expected power plants totaling more than 40 GW would be offline for planned outages on May 18.

An Amazon Web Services data center in Stone Ridge, Va. The PJM Interconnection will be able to curtail data centers and other large loads that have backup generation under an emergency order issued May 18, 2026, by the U.S. Department of Energy

“The projected level of generation outages coupled with the forecasted demand raises a significant risk of emergency conditions that could jeopardize electric reliability and public safety,” PJM said.

The curtailments would be a last resort before ordering rolling blackouts, according to the DOE’s order, issued under the Federal Power Act’s section 202(c). Only large energy consumers with backup generation would be affected.

“The employment of this backup generation is expected to reduce stress on the grid,” the DOE said. “This will permit orderly, safe, and secure operations during PJM’s hot weather conditions.”

There are significant amounts of backup generation in the United States that have remained largely untapped during grid emergencies, according to the DOE.

“Deployment of backup generation resources (whether auxiliary, standby, directly-connected, battery storage or other, and whether synchronized or not to the bulk power system) at data centers (including, but not limited to, hyperscaler facilities), and at other large load industrial and commercial customer sites, can prevent avoidable blackouts, thereby saving lives and reducing costs to the American people,” the department said.

In January, the DOE issued similar emergency orders to PJM, Duke Energy Carolinas and Duke Energy Progress, and the Electric Reliability Council of Texas.

PJM said on Monday that it had issued “maximum generation” and “load management” alerts for May 19, with a “hot weather” alert in place for most of the PJM footprint.

Also, the grid operator activated demand response customers in parts of the Mid-Atlantic and Dominion regions. The grid operator said it called on pre-emergency demand response for the Baltimore Gas and Electric, Dominion and Potomac Electric Power Co. areas on Monday to address local transmission constraints and to preserve the run-time of generators that will be needed for the hot weather and higher electricity demand expected on Tuesday and Wednesday.

For three days starting on Tuesday, PJM expected its peak load to hit 134,027 MW, 135,961 MW and 119,103 MW.