随着极端高温和高湿度席卷美国大部分地区,美国东南部和东北部紧张的电网正面临严峻的可靠性挑战。为应对潜在的停电风险,美国能源部发布了一项紧急命令,允许卡罗来纳州的杜克能源公司(Duke Energy)最大限度地提高发电量。 能源部长克里斯·赖特(Chris Wright)将这些电网脆弱性归因于过去的能源政策,并强调现任政府正致力于通过所有可用的热能发电能力来维持电力供应的可靠性。尽管做出了这些努力,高需求仍将大西洋中部地区的电价推向了极端水平,纽约和新英格兰地区的电网运营商也正为应对进一步的压力做准备。 本文认为,这些反复出现的危机源于美国发电结构的变化,并指出可调度热电厂的退役速度超过了可靠替代能源的整合速度。作者认为,虽然可再生能源在气候温和时有所助益,但在极端天气事件中却无法满足高峰需求。文章指出,未能新建核电能力是一个错失的机会,并建议若要避免未来依赖紧急豁免和需求响应干预,长期电网稳定需要更快地向稳健的无碳能源转型。

相关文章

原文

As the U.S. men's national soccer team kicks off its first match against Paraguay in Southern California on Friday night, large swaths of the country are trapped in what feels like a wet sauna, with dangerous heat and humidity forcing households to crank up their air conditioning and straining power grids from the Southeast to the Northeast.

On Thursday, the Department of Energy issued an emergency order to mitigate blackout risks across the Carolinas amid extreme heat that threatens to sharply increase power demand.

The order, issued under Section 202(c) of the Federal Power Act, allows Duke Energy Carolinas and Duke Energy Progress to run certain generating units at maximum output.

Secretary of Energy Chris Wright stated, "Maintaining affordable, reliable, and secure power in the Duke Energy service territory is non-negotiable."

"The previous administration's energy subtraction policies weakened the grid, leaving Americans more vulnerable during events like this. Thanks to President Trump's leadership, we are reversing those failures and using every available tool ensuring Americans in the Carolinas' have continued access to affordable, reliable, and secure energy to power and cool their homes," Wright said.

Maximum temperatures across the Mid-Atlantic, especially around Washington, D.C., have ranged from the 80s to the 90s, reaching as high as 95°F on Thursday. Some relief is expected this weekend, but temperatures are forecast to rebound next week as heat builds back into the region.

"It's super humid in the Northeast and Mid-Atlantic, but relief is coming by Saturday," Meteorologist Ben Noll wrote on X.

Bloomberg noted that grid stress materialized late Thursday, with PJM real-time power prices rising above $1,300 per megawatt-hour as sweltering heat lingered across the Mid-Atlantic. New York's grid operator prepared to activate emergency demand response, while New England's grid operator declared abnormal conditions as heat indices approached 100°F.

We have seen four-digit territory before. As we covered in April when PJM prices shattered $1,000/MWh after first running during the January freeze to $2,300+, the same structural weakness keeps reappearing. Demand surges, variable resources drop off, and the system leans on whatever thermal capacity can still run.

It is the direct consequence of a generation mix that has shed firm, dispatchable megawatts faster than it has replaced them with anything that actually shows up when the forecast is wrong and the temperature is not. 

The blackout in Spain is a phenomenal example of when this is taken to the extreme. And based on some recent warnings from ERCOT, Texas could be the next example.

When push comes to shove on the electric grid, it's not the renewables that are there to help…

Renewables and batteries help at the margin on good days. They do not solve the evening ramp or multi-day heat dome when every household and every server farm is pulling maximum power. The emergency waiver for Duke is the quiet admission that the current fleet cannot carry the load without violating the operating permits it was given.

Nuclear is the obvious technology that could have filled this gap with carbon-free, always-available capacity. A fleet of new reactors sited years ago would be delivering gigawatts of firm power right now without anyone needing to waive emissions rules or beg demand response programs to shed load.

Instead, the United States has spent the better part of four decades adding almost no new nuclear capacity at commercial scale. As we have documented repeatedly, including in our coverage of the NRC’s new fast-track permitting framework promising 6–12 month construction permit timelines, the regulatory environment has improved dramatically under the current administration. Yet the shovels in the dirt remain conspicuously absent for most projects.

Meanwhile... 

On watch for tropical activity in the Gulf of America.  

联系我们 contact @ memedata.com