德克萨斯州公用事业委员会(PUCT)近日批准了一项净计量协议,允许一座260兆瓦的人工智能数据中心与风电场同址运行,为未来德克萨斯州电力可靠性委员会(ERCOT)市场内的“表后”项目确立了关键的监管范本。 作为批准条件的一部分,PUCT施加了严格的可靠性要求以确保电网稳定。该数据中心被要求在电网紧急情况下,必须在30分钟内将全部负荷削减,必要时需使用物理断路器断开连接。此外,该设施被禁止参与付费的需求响应计划,因为委员会将这种快速关停能力定性为基准可靠性要求,而非自愿服务。 此项决定是对参议院第6号法案(SB 6)的一次重大考验,该法案授权ERCOT在紧急情况下切断大型负荷。尽管一些开发商曾担心该裁决可能阻碍同址项目的建设,但专家认为,只要项目具备充足的备用容量,这就为行业发展确立了清晰路径。委员会拒绝项目特定豁免申请的态度,凸显了德州优先考虑电网容量而非工业负荷同址便利性的立场。未来如科曼奇峰(Comanche Peak)核电站的亚马逊-Vistra园区等项目申请,将进一步明确这一不断演变的监管框架。

相关文章

原文

By Marlene Wilden of UtilityDive

The Public Utility Commission of Texas last week approved a net metering arrangement for a 260-MW AI data center co-located with a wind farm of approximately the same capacity in a case that could serve as a template for other co-located loads in the Lone Star State.

The data center is the second one planned for the site, and the developer had argued it should not be subject to the same curtailment requirements as the first because the total load of both – about 525 MW – exceeds the generation resource’s capacity of 265.5 MW. 

An Oncor substation in December 2025 next to an up to 600-MW Skybox data center in Hutto, Texas. A data center net metering arrangement approved by the Public Utility Commission of Texas on July 24, 2026, could serve as a template for other co-located loads in the Lone Star State. Getty Images

The commission rejected that argument. According to the July 23 order, the data center must be capable of curtailing its full load within 30 minutes during grid emergencies, with physical breaker disconnection if necessary. It is also barred from participating in paid demand response programs tied to the arrangement.

The proceeding represents one of the first major tests of Texas’ SB 6, which became law last year and established new rules for large loads in the Electric Reliability Council of Texas’ territory, including giving the grid operator the authority to disconnect data centers during grid emergencies.

Rather than creating a project-specific exception, commissioners largely adopted ERCOT’s proposed reliability conditions. The order allows the co-location arrangement to move forward while establishing operating requirements for future behind-the-meter projects. 

Chris Talley, co-founder of GridTracker, wrote in a LinkedIn post following the decision that the order is not a “death blow” to co-location in ERCOT.

“It just means that this architecture now essentially requires full backup capacity,” he said.

In a follow-up message to Utility Dive, Talley clarified that by “full backup,” he meant resources capable of carrying the load off-grid for a meaningful period of time, rather than simply riding through a short interruption. He cautioned that this was an “untested assumption” and pointed to a pending co-location application from Amazon and Vistra to build a data center campus next to the Comanche Peak nuclear plant, southwest of Fort Worth, as a case to watch. 

“How ERCOT and the Commission treat that arrangement will be very telling,” Talley said.

The decision requires the data center to operate with greater flexibility than a traditional industrial load. The order states ERCOT should provide 60 minutes’ advance notice “when practicable,” while allowing the operator to voluntarily commit to a faster 10-minute response. 

By prohibiting the project from receiving compensation for reducing its load during grid emergencies, the order distinguishes mandatory emergency curtailment from voluntary grid services. The ruling treats the ability to rapidly shut down as a reliability requirement for operating behind generation.

Crusoe, the developer of the AI data center, and Ensign, the large load customer that plans to operate the site, argued that forcing the entire site offline was disproportionate and that additional curtailment was unnecessary after the earlier reliability condition on the co-located wind project. Commissioners largely adopted the administrative law judge’s recommendation, including revisions from Chairman Thomas Gleeson, and concluded that allowing the second load to remain online while the first is curtailed would undermine the goal of ensuring generation capacity is available to the grid during emergencies. 

The case also attracted filings from the Texas Competitive Power Advocates and natural gas producer BKV, which argued the proposed framework could discourage future co-location projects. PUCT staff contended those parties lacked standing under the governing statute, and the commission’s final order did not address their arguments.